Helen Khamooshi November 19, 2020

I am using Jira Next-gen projects (standard version) and I am the org admin. I would like to be able to see the schedule bars like the image in the section (Plans with the improved interface) in this link => https://confluence.atlassian.com/advancedroadmapscloud/overview-998650995.html 

I can see the timeline for the epics but I really need to see the deadlines for each sub task/ sub issue as we have client deliveries as sub issues under the epics. It looks like next-gen projects can't the link I provided above.

Has anyone got a solution? 

Many thanks

1 answer

1 accepted

0 votes
Answer accepted
Walter Buggenhout
Community Champion
November 19, 2020

Hi @Helen Khamooshi ,

The link you shared points to Advanced Roadmaps, which is a feature of the Jira Cloud Premium plan. They are not available in the standard plan.

The roadmap you have in your standard plan does not have the ability to drill down into subtasks. There is an open issue for it in the backlog that you can track here: JSWCLOUD-18677 

Helen Khamooshi November 19, 2020

Thank you very much @Walter Buggenhout. I have been searching the documentations forums and gathered that but wasn't sure if that was the final answer (I was hoping there was a solution but clearly not!)