Hi all, I've a bit of a head-scratcher here. I'm a project manager of three teams using v6.2, looking at an agile board. Each team has their own board, based on unique queries of the same project. Help was needed from team one, so team two created a ticket and added the correct component to appear on team one's board. I looked at the ticket directly, saw nothing unusual, added it to sprint and assigned it to an engineer on team one. The engineer received notification and started working, but it never showed up on the in the active sprint board. It is visible in in sprint in the "backlog" view. it is visible in the "reports" view. But in the "active sprint" view (which is reached by pressing "2") it does not appear.
What could I be overlooking that would allow a task to be visible in only two of the three views of JIRA agile?
-B
I have had the same issue, but the re-indexing feature is not available anymore. What I have found out however, helped me to resolve it in my case.
I had a scrum board with a filter on multiple projects + certain label. I had swimlanes by Epic on this board. Some tasks were not shown on the active sprint board, though they were in the sprint (they appeared on the backlog in an active sprint). Even in the board settings in column mapping section the count of the issues per column was not the same, as was actually shown on the board.
I have figured out, that removing swimlines results into showing all my lost tickets.
Why? Apparently, some epics were not filtered by the board filter - they were either from different projects, or didn't have required label. As a result - those epics did not show on the board as a swimlines, together with any tasks that belonged to them.
That was my issue, hope it can be helpful for others!
Thank you!!!! I was troubleshooting a board with a really funky config and this turned out to be the solution.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thnak you Catherine. It fixed my issue (issues were showing up in sprint in the backlog view but missing from Sprint view - which swimlanes by epics).
I too was using a convoluted Board Filter Query (this project and that project and the other project but not this component, plus all tasks with a magic label, plus all tasks owned by specific individuals).
It turned out that the Epic was unowned, and the missing tasks all belonged to such an Epic (whose project is outside the main filter query).
Fixed by assigning the Epic to an individual defined by our query,,,,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
We ran into the same problem and it was fixed by a project re-index. Our sprint board did have epics as the swimlanes, so that may be a cause of the problem.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
I had the same problem, only solution which helped me was to Base Swimlanes on Projects not on the epics.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
For me, I found out what the "missing" issues had that made them appear in the Board (look at your Filter Query), then discovered that the Epic that contained the missing issues didn't meet the Board Filter Query conditions. In my case, I just had to assign the Epic, since my board filter query is a mix of projects, labels, and assignees.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I have two ideas:
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Nick, As noted, the ticket was in sprint and was visible in every area except for the active sprint view. To recap: * If I chose the agile board from JIRA's agile dropdown and pressed "1" to for the backlog view, I could see the ticket in sprint. * If I chose the agile board from JIRA's agile dropdown and pressed "2" to for the active sprint view, the ticket IS NOT VISIBLE in sprint. * If I chose the agile board from JIRA's agile dropdown and pressed "3" to for the backlog view, I could see the ticket in sprint. As such, the permissions checker and other diagnostic tools don't identify any issue with security or access. Alas, the sprint has come and gone, and the task is now resolved so this question is now pointless. Thanks anyway!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Bryan,
So you didn't solve it at the end?
I have same issue now...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Exactly the same problem - so I set the db to re-index and suddenly.. they all appear on the board when I click on "Active Sprints"
I say "suddenly"....what I mean is after some considerable time re-indexing our global Jira !!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
So Re-indexing might likely solved this problem !!
May i know what could have caused this problem ?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
@Anilkumar B As I mentioned in response to Nick, no solution came in time for me to identify and definitively solve the problem. However @kevin conroy seems to have had the same problem and found success by reindexing. Give that a try!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Bryan Collick,
I had tried with full-index but no luck,
Am running out of the ideas,
Best Regards,
Anil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I have exactly the same problem as described by Bryan back in 2015. We are running Jira v7.2.2 and here is how the problem unravelled (I am pretty sure by following below steps the problem can be recreated too but cannot confirm that since have not tried):
1. 2 Stories with To Do status were taken out of the active Sprint 1, re-estimated and added to Sprint 2 instead (which will be starting in 2 days time). The same developer name has stayed assigned to the stories.
2. The Sprint field in both tasks shows the correct value of "Sprint 2"
3. Once Sprint scrum board is refreshed the two items disappear from Sprint 2 (which as mentioned has not started as yet) and are moved to backlog. The two items are still showing Sprint 2 value in the Sprint field if stories viewed. At the same time the effort estimation total value for Sprint 2 goes down by the effort estimation total specified for the two stories.
4. I tried all sort of things, deleting/adding labels, components and different things but none of it work except for cloning 2 stories (including the links) which fixed the problem and the clones stay in the Sprint 2. I deleted the two original story tasks.
This has happened 2 more times and I was wondering what the potential problem may be here and whether any of you managed to get of the bottom of this issue. Creating clones and deleting original is far from sustainable solution. I will speak to our admins and see whether re-indexing can be performed.
Many thanks in advance for any suggestion the forum may have.
M
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.