Hi @李国庆 Zoe ,
Logwork的时候只需要填写Time spent,注意这时候Time remaining默认是灰色的
系统会根据Original estimate去自动计算Time remaining,如果你同时填写了Time remaining,系统会认为你在log 30m后,剩余工作量依然还有30m,等于做了重估算
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Ollie Guan 很感谢能回答我,想再问一下,Time spentOriginal estimate都设置了的话,是有什么影响吗,还是time tracking主要是以Original estimate这个来计时的吗?那Time spent的作用是在哪里呢
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
举个例子:
一个Task创建时初始估算4小时,工作的第一天,员工A登记工作量3小时,默认此时剩余工作量还有1小时;
如果此时员工A除了登记的3小时外,还把剩余工作量改位3小时,意味他对这项任务做了重新的估算,一共需要6小时才能完成(已花费3小时,并且还需要3小时才能完成)
time tracking中各字段都有其价值:
1.在燃尽图里,Original estimate显示了最初的估算基准,而Time remaining则是实际的燃尽速率
2.在工作量报表中,Time spent则体现了每天的任务工作量消耗
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
看下这里吧,如果你是希望用结束时间-开始时间来计算Time Spent,我觉得Automation是不支持的。
You can use date and time smart values to dynamically set the date started, and text smart values to customize the description.
https://support.atlassian.com/jira-software-cloud/docs/automation-actions/
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.