Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Remaining estimate does not recalculate itself after Original Estimate is updated

Shravan K February 23, 2018

Hi, we use JIRA cloud instance to track our product development.

Often our developers required to allocated more hours than what is estimated.

The problem we couldn't figure out a solution was when the "Remaining Estimate" is reduced to '0'. 

We understand Remaining Estimate is deprecated with the time logged from the original estimate until it is reduced to '0'. 

Now in our situation when we update the 'Original Estimate' field, we were expecting that the Remaining Estimate field would automatically recalculate and update itself and would now show up >0 value that is to say there are few hours left until completion.

But this is not the case and the Remaining Estimate is stuck at 0 after it is reduced to 0.

Any insights would help?

Thank you,

3 answers

1 vote
Jamie Wilbraham
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 21, 2019

It would be good if the field recalculated if no time has been logged

1 vote
Sakshi Mittal November 15, 2018

Hi Soane,

If Remaining estimate field wont recalculate, its better not to show it in the first place with incorrect information. This doesnot make any sense. Remaining field should be calculated each time.

Is there any plan on fixing this?

 

Best Regards

Sakshi

1 vote
Soane
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
April 6, 2018

Hi Shravan,

Remaining Estimate field won't automatically recalculate and get updated, I'm afraid. However, you can manually update this information by editing the issue.

Cheers,
Soane K.

Suggest an answer

Log in or Sign up to answer