Require Original estimate before Work logging

odanu-axa February 28, 2013

Hi,

Is there a possibility to require the task to be Originally estimated before first work log.

I mean, I do not want to have logged work on tasks, which do not have any estimations.

Thanks.

2 answers

1 accepted

0 votes
Answer accepted
Viðar Svansson [Tempo]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 28, 2013

Have you tried logging work in Tempo on issues with no original estimates? It sets the orginal estimate to time spent + remaining estimate.

odanu-axa February 28, 2013

The ideea is to force developer to think on estimations, not just to hack the system:)

Viðar Svansson [Tempo]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 28, 2013

Well he has to think about the estimation. That is what he enters in the remaining. He sees that there was no estimation set and has to think about it :)

Would you like him to enter the original estimation at the same time? He would them enter what he spent + what he thinks is remaining as original estimate. Which is what Tempo does automatically.

Is that not the ideal solution?

odanu-axa February 28, 2013

As I can see it is a commercial solution, is there any three solution?

odanu-axa March 2, 2013

As I can see it is a commercial solution, is there any free solution?

Viðar Svansson [Tempo]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 5, 2013

Not that I know of.

0 votes
Chung Park Chan
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
February 28, 2013

You can configure the Time Tracking field to be Required in the Field Configuration Scheme. That way, each successful new issue creation must have the Original Estimate set.

Hope this helps.

odanu-axa February 28, 2013

It does not help me, as a new created issue, in our case, should not immediately have the estimations. This is because there are lots of cases when we create issues, put them in backlog and only the person that begins working on that issue, or logs the work on it, should estimate it.

Theinvisibleman
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
February 28, 2013

Hi Oleg,

If that is the case, you might want to take a look at some of these other Answers posts that talks about making a field required based on another field :

https://answers.atlassian.com/questions/54234/how-to-show-and-hide-specific-customfields-based-on-another-customfield-values

https://answers.atlassian.com/questions/70973/how-do-i-make-a-field-required-based-upon-the-value-of-another-field-set-in-workflow-transition-screen

These methods might require a bit of work, though, as certain plugins are required to achieve this.

odanu-axa February 28, 2013

I can't understand how your solution might help me? I just need to be able to verify if Original Estimation exists before first work log.

Theinvisibleman
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
February 28, 2013

Hi Oleg,

I figured that it could help in your situation by making the Work Logging field dependent on the Original Estimate field. This way, the Work Logging field would only be available for edit once the Original Estimate field is filled.

odanu-axa February 28, 2013

Any other simplier solutions?:)