I am attempting to roll up story points to their epics when there is a trigger on the stories story point field is updated so I have an up-to-date sum of the current points for an Epic.
This was working and then all of the sudden it is no longer working as expected, previously I was getting the sum of the points of the child stories, now it would seem we are looping over many more story for an epic so the resulting story point value is large.
As @Bill Sheboy said
If you are on a "next gen"/ "Team-managed" project you will need to use "Story point estimate" and Parent" but I wasn't sure where I needed to do each.
Attached is the screenshot of what I got to work.
Hi @Neil Wills
And...I wonder if the recent work to fix/improve EMPTY tests in JQL is causing a problem. You could check that by modifying your rule to write the trigger issue epic link, and the lookup issues keys, to the log to check.
Best regards,
Bill
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.