Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Scope changes during sprint after sprint planning in JIRA

Agnieszka
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
June 8, 2016

I'm looking for a report or JQL query to present scope changes during a sprint but after the sprint planning session: how many new tasks have been added during the sprint (after planning), how many tasks have been removed, how much time was planned and how much time has been spent.

1 answer

0 votes
Nicolas Bourdages
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 8, 2016

That's exactly what the Sprint Report is for in JIRA Software. You're doing scrum using only JIRA core?

https://confluence.atlassian.com/jirasoftwarecloud/sprint-report-777002722.html

 

Suggest an answer

Log in or Sign up to answer
TAGS
AUG Leaders

Atlassian Community Events