Show projected burndown rate/completion date

Shawn
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
June 26, 2018

Hello,

We currently have a sprint (our first as a team) where we have around 5% of the work completed. We originally estimated time on all the tasks to be the same. We are already behind schedule based on the burndown report/chart. Is there a way to have the report show a red projected (dotted line) to when we would finish at our current rate of task closure?

Thank You.

1 answer

0 votes
AMIT GULATI
Contributor
June 26, 2018

Although not at the sprint level but you can use version report to see predicted dates for the release, if you have finished 10% of the overall work for the release.

If you are using portfolio, it too can show you forecasted dates for the release.

Hope it helps