Sprint Start and End Date Calcualtion

Deleted user October 16, 2019

Hi, 

Want to know whether sprint start TIME is considered during calculating the sprint duration (end date). 

 

Given a 2 weeks sprint (10 days - considering 5 days a week). If we a sprint start on day 1 2:00pm. Does it would end on 11th Day 1:59pm or it would end on 10th day 1:59pm. 

 

Does it consider time (hours) while calculating the duration of sprint.

1 answer

1 vote
Nisha Hajamohideen
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 16, 2019

When you start a sprint, wen you give a name and duration of 2 weeks, by default the start date is set the time you start the sprint and the end date is 11th day the time.  However, you can update the start and the end time. 

Jack Brickey
Community Champion
October 16, 2019

As an example of this...

EB36797B-FFED-4987-BDE6-2952E2D76504.jpeg