Andrew Bushara
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
September 25, 2019

Currently, the "work complete" attribute on the sprint health gadget is defined by any ticket that is in the current sprint that is marked as "Done" for the status.

My question is, is it possible to also make it so the "work complete" is flagged by tickets with as status of "Done" OR "Ready for production"

2019-09-25 17_16_37-Andrew test dashboard - Jira.png

 

I can currently edit this query when I click on the "Work complete" section of the graph (see screenshot below), however, I wanted to know how I can save this change in this graph.2019-09-25 17_20_35-[MMAIA-3777] eshepherd password reset - Jira.png

Any help would be much appreciated.

2 answers

2 accepted

1 vote
Answer accepted
Jack Brickey
Community Champion
September 25, 2019

The health gadget considers done to be any issues in the far right column of the scrum board. So if you place the ready for production status into that column it will count as done in the gadget. 

Andrew Bushara
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
September 25, 2019

Hey Jack, thanks for the swift reply! Excuse my ignorance but can two columns on the scrum board be put in the far-right column and be considered as 'done' in the gadget?

0 votes
Answer accepted
Jakub Sławiński
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 4, 2019

@Andrew BusharaAs Jack wrote, you need to put both statuses in the last column. By doing that you will achieve what you want.