In backlog, I can see Scrum sprint 5 and Backlog, but when I go to task and for task select Sprint I can see Scrum Sprint 1 which doesn't exist or it might exist somewhere, but I cannot find it. Please tell me how can I find it?1.PNG

1 answer

0 votes
Benjamin
Community Champion
May 11, 2020

Hi @Dinmukhamed -

 

This might happen if you running multiple scrum boards in a project. Another board have this sprint. One way to find it, is to have board to view your entire project so that you can see all the sprints that are open. 

You also can list all the sprints in filters as well.

 

Hopes this answers your question. 