Start(ed) sprint vs aka future sprints, how it all works

Mario Trento
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
September 30, 2016

Hi,

Looks like I can start Sprint no matter what start/end dates are, in this case what all call "Future" sprint? is only base on date range ??

I also see that once Sprint started (have those 3 status color cirles) then you can not delete it, even if no issues are assigned to it.

I appreciate if anybody can help me with those definitions.

 

Tx

Mario

1 answer

0 votes
Peter Geshev
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 1, 2016

Hi Mario,

According to JIRA terminology a future sprint is a sprint which is being planned but has not been started. Also you can delete only planned sprints(sprints that are not yet started).

Regards,