Story points assigned vs completed during end of the sprint

vinit_kumar
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
March 27, 2020

How can I get consolidated report for total number of story points assigned vs total number of story points completed for a particular sprint for every particular team member right before the sprint is closed

2 answers

0 votes
Aditya Sastry
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 31, 2020

@vinit_kumar You can use sprint health gadget. This will give you the progress of sprintsprint health gadget.PNG

0 votes
Petter Gonçalves
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
March 30, 2020

Hello @vinit_kumar

Thank you for reaching out.

I believe the velocity report might provide you all the story points committed and completed in your Sprints at any time you want:

View and understand the velocity chart

Basically, the Velocity Chart shows the amount of value delivered in each sprint, enabling you to predict the amount of work the team can get done in future sprints. It is useful during your sprint planning meetings, to help you decide how much work you can feasibly commit to:

Screen Shot 2020-03-30 at 20.50.43.png

Please, take a look at the documentation provided and let us know if this is the report you need.