Had an issue in a sprint that:
The problem is that the 3 points aren't being added to the sprint velocity for number of points completed in the sprint. Ideas why?
JIRA Agile says so when you start the sprint - if there is an unestimated issue when you start the sprint, any estimates on this issue later on will not be added.
In order to include it in the total number of points for the sprint, you would have to remove the issue from the sprint and then add it again.
I assume the reason behind this is to provide a decent metric on scope change, e.g. scope creep.
thanks for the info - helps a lot. Yes, trying to make our metrics real and meaningful.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Can I do the remove and add to the sprint after the sprint has been closed?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I believe the answer can be found here: https://answers.atlassian.com/questions/141766 :)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.