Hi Team
The solid bars at the beginning and end of each task are a good enough indicators of the the fact that its a fixed duration task and hence i want to get rid of the pin icon highlighted in yellow below from the gantt chart. Is this achievable ?
Thanks
Hello Manali!
This is Alexey from ALM Works,
there is an option to hide all indicator icons:
Please, note that turning Task Indicators off will also hide other icons like Agile Mode, etc.
Best regards,
Alexey
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
awesome thanks.
another qq @Dave Rosenlund _Trundl_
I am trying to get the gantt chart to use a formula field ('Progress' in pic below) for progress calculation. Even though it mentions here that I can use any other field apart from work estimate the options are limited. How can I achieve this ?
'Progress' formula field is based on Status and ignores parent issue + no 'Apply Resolution'
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.