Peter July 14, 2018
Is there a version that supports the ability to show the roll up of sub tasks for project management tracking

3 answers

1 accepted

0 votes
Answer accepted
Ollie Guan
Community Champion
July 14, 2018

Hi @Peter,

What kind of presentation do you need? What elements are included?

BTW:Jira Server or Cloud?

Peter July 14, 2018

It’s jira server. The view I would like to share with my team is to show a list of sub tasks below main task. Similar to the way msp indents sub tasks in a gant chart

Peter July 14, 2018

My company does not have it but it’s prob what I need. Thanks

0 votes
Anneke Schadle September 12, 2018

Thanks, I'm sorted

 

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
July 14, 2018

It's been built in since Jira 2, if you are looking at the estimates and work-logs.

There's a panel in the issue view that shows you estimate, logged time and remaining.  It has a toggle in it for "include sub tasks".  In the issue navigator, there are a couple of fields you can add to the display for showing the time on the current issue, but also the same fields prefixed with Σ to show the summed up values.