Slightly stuggling with this, maybe it's something I am doing wrong in Google calendar.
I setup an 'issues calendar' widget on a Jira dashboard and clicked the 'Export in iCal format' link underneath it. I import the iCalendarExport.ics into Google calendar using the web interface (other->import calendar) and the issues appear in my calendar and are synced to my iphone.
I have noticed however that if I now go and add another issue to the Jira dashboard calendar this is not reflected in my google calendar. It's almost as if I've just done a one-time import rather than subscribe?
Any ideas?
Well, the iCal that you export only contains a subset of issues right? Unless its a link to resource itself, what you'll only get is a subset of issues.
You'll need to search for a proper integration for this (https://zapier.com/zapbook/google-calendar/jira/).
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
What I did was setup a custom issue type 'milestone' and these are used throughout several projects defined using the 'due date' field. As I say it works fine the first time you import, but if you go and add a new milestone afterwards it will not appear in the calendar.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.