Hello,
I have a task "A" that starts on March 1, 2022, and ends on March 5th, 2022. This task is a predecessor of task "B" which starts on March 10, 2022. The lag time is 5 days between the tasks.
Now the puzzle starts... When I change the start date of Task "A" from March 1 to March 8th the start date for task "B" remains the same BUT it should be automatically be updated to March 13th.
Please, explain to me what I am doing wrong
Thank you in advance
It can be achieve via automation.
Step 1: Create Custom Field (Label Type) name as predecessor and add the issue key of predecessor issue.
Step 2: Create automation rule when Predecessor field edit and is not empty then Lookup issue for and use the smart value of Predecessor field.
Step 3. If lookupissue size equals 1 then edit the current issue Actual start date with a smart value "{{lookupIssues.Actual End Date.plusBusinessDays(1)}}" and set the end date as {{lookupIssues.Actual End Date.plusBusinessDays(issue.customfield_10212)}}.
Am I considering that the connection between Task A and Task B is block by/ is blocked by?
If yes, i think there's no way for the automation.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.