Suggestion: Include Count in Sprint Report

y_masam
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
May 27, 2025

I was reviewing the Sprint Report for our past sprints and wanted to get the count of all issues that were completed and those that were carried forward to other sprints.

While I can see the list of issues, I currently have to count them manually. It would be really helpful if the report could also display the count for each section.

Thanks!

2 answers

1 vote
Danut M _StonikByte_
Atlassian Partner
May 28, 2025

Hi @y_masam,

You can use Jira's Burndown report instead of Sprint report. This one lets you display the chart/report by Issue Count and will display the remaining issues at the end.

image.png 

Danut.

0 votes
Sanam Malleswari
Community Champion
May 27, 2025

Hi @y_masam

Welcome to the Atlassian Community!

Hope below ways will be helpful for you.
1) On the Backlog page UI, you can see how many issues are Open, In Progress, and Completed. Just click on each color segment to view the corresponding issues. Please observe below image.
Screenshot_27-5-2025_123231_tpicap-npd.atlassian.net.jpeg
2) You can create filters using JQL (Jira Query Language) to count issues:
    Completed Issues in a Sprint - JQL: sprint = "Sprint Name" AND status = Done

Karan Sachdev
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
May 27, 2025

Hey @Sanam Malleswari

Just a slight correction here, the different colour segments in the backlog show the total story points for each of the status categories: To Do, In Progress and Done.

Grey one is the total story points of all issues (work items) in the To Do category and so on.

It doesn't show the number of issues in each status category.

Thanks!

Like Sanam Malleswari likes this
Sanam Malleswari
Community Champion
May 27, 2025

Hi @Karan Sachdev

Thank you for the clarification. You're absolutely right — the colored segments in the backlog indicate the total story points by status category (To Do, In Progress, Done), not the count of issues. Appreciate the correction!