Is it possible to plan time to an issue and break it down by worklog attributes?
For example - our analyst will have a new development project that total has 70 hours for them. We break it down in the work log attributes by phase of work. Can I plan work for this BSA to one issue but by the specific hours per phase?
Hi,
This feature is missing in my mind. The opportunity to plan work and plan ressources to the good job.
A JIRA issue represents a sum of different work test, design, dev ...
Hi Andrea,
this is not possible in the current version of Tempo Planner. The "smallest" unit you can plan time on is the JIRA issue. The worklog attributes are a Timesheets feature and can only be added to worklogs.
Regards,
Susanne
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.