I would like to use Tempo to plan work for 80 people on a software development team. I need some help with best practices.
1) I have specific requirements like managing part time resources - how do I set workday different for each user.
2) How to plan time that is initially to a team and then to an individual. I have specific reporting requirements that include viewing capacity / plan - overall, at a team and at an individual.
Please suggest the best resource to assist with setup and reporting.
Thanks!
Hi Brad,
1) Have a look at the Workload Schemes in Tempo to configure each user differently.
2) It is currently not possible to create a plan without specifying a user. Please track this issue for status.
Cheers,
Viðar
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.