Hi there,
We have issue in getting sprint reports. Let me explain it in an example:
on Sprint #1:
on Sprint #2:
Hope you to understand our problem and happy to read your solutions or guidance.
Thank you.
We use JIRA 7.12 server version.
I believe the problem you are having is that JIRA is not designed to have incomplete work carried across sprints.
Work should be planned to be closed within a single sprint. (Agile/Scrum framework)
This would explain why the same story, being tagged with two subsequent sprints, has a total time of 3 days (for both sprints).
If the story had continued into a 3rd sprint, then 3 sprints would reflect the total time spent (effectively tripling the total time spent).
Conclusion: Ensure work is planned and completed in one sprint (i.e. no carry-over).