The original time estimation of the parent story doesn't sum up for the total time estimations of sub tasks. How to activate this?
example:
Story - A
Sub task - a1 - Original time estimation: 2h
Sub task - a2 - Original time estimation: 1h
After manually entering these time estimations in the sub tasks, why doesn't it get automatically added to the Original time estimation of Story A as 3h? How can I get this done?
Hi Harshi,
there should be a checkbox in the parent task right beneath the time tracking which states something like "Include sub-tasks".
You need to check the box, then the sub-tasks time will be added to the parents time tracking.