Time Estimates doesnt show properly in the spring summary

Vishnukumar Vasudevan
Community Champion
August 15, 2012

We have implemented Agile process for the tasks assigned in on of projects. Currently, we added three sprints and started working.

We added Time Estimate and Time Spent in most of the tasks. From the below screen shot, these entered estimates are not being updated in the sprint summary.

Something goes wrong in the calculation.

Would you be able to help us here ?

We use JIRA 4.4.1 and GH 5.7.4

2 answers

1 accepted

0 votes
Answer accepted
Vishnukumar Vasudevan
Community Champion
October 9, 2012

This is fixed. Was a usage issue.

0 votes
Theodore Tzidamis
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 6, 2012

Hey Vishnu,

Feel free to check this page, that one might prove useful. In short, let us check:

  • Do the versions have a start and end date?
  • If so, are the logs actually logged inside that range?

Theo