Hi,
Many of our Issues are closed with no Time Spent being entered (making the Burndown chart look strange), so I'm wondering what I can do to 'help' team members enter this information.
So I'm wondering if 2 things are possible when dragging an issue to Done?
By the way, we have already automated the setting of Remaining Time to zero when Done (via a post function), but want to square away Time Spent also.
Any thoughts greatly appreciated.
Regards
Mick
Mick, just like Steven said... you can make "logging work" required on certain transitions via JIRA Workflow Validators or JIRA Workflow Properties.
Thanks for the quick response - I'll try it out. And thanks for the links Gabrielle - that's saves me time looking for them.
Mick
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Glad we can help you out
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You can mark the field as required during a Workflow Transition using a Validator.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.