Time Spent report - Is there any way to calculate effort variance per sprint ?

DEEKSHIT NAYANAR
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
June 27, 2019

If i commit 5 itmes in a sprint with original effort estimate as 20,10,5,5,10 respectively. Out of which the first item estimated at 20 hrs gets spilled over. Say i have worked for some 15hrs on that item and i still need 20hrs to complete the item (Basically my original estimation was incorrect). Then when i move it to the next sprint with 20hrs added and then if i try to generate a time report of effort variance , it adds up the initial estimated time as well and not the effort that i estimated only for the current sprint. 

Only if i get a difference between estimated and logged in each sprint , i would be able to calculate effort varience per sprint. 

Is there any way to calculate effort varianc eper sprint ?

1 answer

0 votes
Johannes Krist
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
July 3, 2019

We do manually in my team:

Effort variance

Effort Variance represents the comparison of the effort that was planned (Estimated story points) against the actual efforts (achieved story points) with in all iterations contributed towards a release

(Effort Variance = Estimation SPs – Spent SPs)

Razia Allen May 31, 2025

Is there any report in Jira that will show you this information by user story  