Time estimates for tasks with sub-tasks

JorjGaidin
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
June 15, 2023

Is it possible to view the time estimate of a task as the sum of the tasks of it's children?  I can see the time remaining does the calculation but the original estimation field doesn't auto populate with this informaiton

1 answer

0 votes
Deepak Jain
Community Champion
June 15, 2023

Hi @JorjGaidin - Welcome to the Atlassian Community !!

This is possible from Sub-task > Parent Task / Story level. When you've added the original estimates in at sub-task level, go up to the Story and in time tracking there is a checkbox to "include sub-tasks" estimates / time remaining.

Hope this helps !!