Is it possible to view the time estimate of a task as the sum of the tasks of it's children? I can see the time remaining does the calculation but the original estimation field doesn't auto populate with this informaiton
Hi @JorjGaidin - Welcome to the Atlassian Community !!
This is possible from Sub-task > Parent Task / Story level. When you've added the original estimates in at sub-task level, go up to the Story and in time tracking there is a checkbox to "include sub-tasks" estimates / time remaining.
Hope this helps !!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.