How can I get a clear report about how many hours are originally estimated and how many hours are spent BY SPRINT (per issue, per person)?
We have some "process" issues, which are included in many sprints and when I take a simple JQL I see a number of all logged hours in issue, but I need to see time report only for a current sprint.
Thanks!
I'd simply add 'Sprint in openSprints()' to the JQL you're using and you're golden.
Let me know if it helped.