Two plans in the same program both show the same epics

gianrico
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
January 25, 2024

Hello

I have created a Program and added two plans.
The issue I have is in the program, I can see the two plans(with epics) but one of the two plans incorrectly reports the epics of the other plan. 

If i go to the plans themselves, all is OK

Maybe i am not using this feature correctly or is that a bug?

thanks

gianrico 

1 answer

0 votes
Mohanraj Thangamuthu
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
January 25, 2024

Hello, Good day. If I understand correctly you have created a project and have created boards. Same Epic is shown on both the boards ? (If this is the scenario, you can go to board settings and change the JQL filter used on the board to required value)

 

Or if you are using Advanced roadmap plan, you can go to issue source of the plan and change the source to required one. Thanks

gianrico
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
January 26, 2024

Hi
I am using advanced roadmap plan
I understand the issue now

The two plans use the same project as issue source. Within each plan i filter epics by labels. So they show different epics.

While in the program that has the two plans, there is no possibility of filtering by labels, so the two plans they both show the entire epics of their project. 

It looks like by design, anyway it would be nice to be able to filter from within the Program. 

thanks 
gianrico

Like Mohanraj Thangamuthu likes this

Suggest an answer