Unable to enable "sprints" in a company managed project

Zac Kennedy October 11, 2021

This may be a very stupid question, however, I am unable to enable sprints in Company Managed / Software project. Did I create the project incorrectly? 

2 answers

1 accepted

3 votes
Answer accepted
Zac Kennedy October 11, 2021

Don't worry - I am an idiot and selected Kanban and not scrum

Carlos Garcia Navarro
Community Champion
October 11, 2021

Don't be hard on yourself! :-)

I'm glad you found the answer, and keep asking questions.

0 votes
Sergio Melo May 30, 2022

Hello @Zac Kennedy 

 

I had the same situation and solved it by creating a new Scrum board in the same project:

- In the left column, where is the list of boards, select +Create New Board,

- Create a Scrum board,

- Option Board from an existing project and

- Fill in with the information about your existing project).

 

Ben Hu
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
July 26, 2023

Thanks I would really appreciate if the documentation have said only Scrum board in company managed projects. 

The key is to have a Scrum board not a Kanban board. The good thing is you may have multiple quantities and types of boards for one project. Just go ahead and create a Scrum board on a existing project and you will see the sprints.