This may be a very stupid question, however, I am unable to enable sprints in Company Managed / Software project. Did I create the project incorrectly?
Don't worry - I am an idiot and selected Kanban and not scrum
Don't be hard on yourself! :-)
I'm glad you found the answer, and keep asking questions.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello @Zac Kennedy
I had the same situation and solved it by creating a new Scrum board in the same project:
- In the left column, where is the list of boards, select +Create New Board,
- Create a Scrum board,
- Option Board from an existing project and
- Fill in with the information about your existing project).
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks I would really appreciate if the documentation have said only Scrum board in company managed projects.
The key is to have a Scrum board not a Kanban board. The good thing is you may have multiple quantities and types of boards for one project. Just go ahead and create a Scrum board on a existing project and you will see the sprints.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.