the original Estimate field is available on my planning lab when i create an issue...but now i want to introduce the origina estimate for issues which are already created...but that does not seem to work,....i can see the planning lab,,but when i click on it I do only see Gant option Milestones.no way to fill in the original estimate.....is there a way to put original estimate on issues already created ??
Look for time tracking rather than original estimate in the list of fields to add to the screen - try that instead. (The estimate and time tracking fields are actually all one field, displayed differently)
Here you have additional information about time tracking:
https://confluence.atlassian.com/jira/configuring-time-tracking-185729592.html
Hello,
You can add Time Tracking to the issue's edit screen and it will allow to change the original estimate.
Be careful that once you have logged work on an issue, Original Estimate will be replaced with Remaining Estimate and you will no longer be able to update the Original Estimate.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.