Hi guys,
I have been able to reproduce this a couple of times, just wanted to ask if it is a known issue. Here is the scenario:
- Sprint 1 completes on Tuesday at 5.30.
- Sprint Planning starts at 9.30 on Wednesday for Sprint 2.
- At 2pm, before Sprint 2 is started in Jira, an issue is closed.
- It has an estimate of 8 Story Points on it.
- It was part of the Sprint 1 commitment, but not completed before the end of that Sprint.
- When Sprint 1 completed, the issue went into the backlog for Sprint 2.
- At 5pm, Sprint 2 is started, with a start time of 5pm, and a commitment of 100 SP.
- The Burndown shows the starting commitment of 100 SP.
- The Sprint Report for Sprint 2 shows that an issue was completed outside the Sprint, with 8 SP. This was completed in the 'dead zone' while sprint boards were not available..
- Sprint 2 rolls on, and the team eventually hits their target, closing all 100 story points.
- However, when Sprint 2 completes, the Velocity Report looks a little off:
- Commitment is 108 SP
- This was increased by 8 SP for the issue closed outside the sprint.
- Completed is 100 SP
- This was not increased by the same 8 SP
(?) Is this a known issue with the Velocity Report?
(?) Or should I set the start time of the Sprint to be 9.30 am?
All input welcome!
Many thanks,
Paddy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.