Hi Team,
I'm capturing agile metric for my project.
So wanted to check for the velocity.
Though there is velocity chart available, but it shows up only for last 5 iterations.
Hence had to go for manual calculation.
Manual calculation logic and chart output is giving different data.
explanation is as follows:
My understanding is,
Commitment Story points = All story points in an iteration that was planned to be completed (which may have been removed or incomplete at the end)
Completed Story Points = All story points that has been completed at the end of an iteration
My query is on commitment story points for Velocity chart that is as follows
Velocity for iteration/Sprint 48 is
Commitment = 74
Completed = 34
but with manual calculation
Completed Issues(32) + Issues Removed From Sprint(10) +Issues Not Completed(67) =109
so as per graph/chart its 74 whereas by manual calculation its 109
Report and data is given below for reference
image2015-7-30 12:13:12.png
Click on customer-sprint 48
View Customer - Sprint 48 in Issue Navigator
Closed Sprint, ended by KING, David27/May/15 9:47 AM - 10/Jun/15 10:00 AM Linked pages
Completed Issues
Key | Summary | Issue Type | Priority | Status | Story Points (32) |
Story | Minor | Closed | - | ||
Story | Minor | Closed | 1 | ||
Story | Minor | Closed | 2 | ||
Story | Minor | Closed | 3 | ||
Story | Minor | Closed | 3 | ||
Story | Minor | Closed | - | ||
Story | Minor | Closed | 3 | ||
Story | Major | Closed | 3 | ||
Story | Minor | Closed | 3 | ||
Story | Minor | Closed | 2 | ||
Story | Minor | Closed | 2 | ||
Story | Minor | Closed | 3 | ||
Story | Minor | Closed | 3 | ||
Story | Major | Closed | 1 | ||
Story | Minor | Closed | 3 | ||
Story | Minor | Closed | - | ||
Story | Minor | Closed | - |
Key | Summary | Issue Type | Priority | Status | Story Points (67) |
Story | Medium | Development | 1 | ||
Story | Medium | Development | 1 | ||
Story | Medium | Development | 1 | ||
Story | Medium | Development | 1 | ||
Story | Medium | Development | 1 | ||
Epic | Minor | E2E Testing | - | ||
Story | Minor | Development | 2 | ||
Story | Medium | Test | 3 | ||
Story | Minor | Test | 5 | ||
Story | Minor | Ready | 5 | ||
Story | Medium | Development | 3 | ||
Story | Minor | Test | 8 | ||
Story | Minor | Development | 5 | ||
Story | Minor | Development | 8 | ||
Story | Minor | Ready | 3 | ||
Story | Minor | Development | 5 | ||
Story | Minor | Ready | 5 | ||
Story | Minor | Development | 3 | ||
Story | Major | Test | 3 | ||
Story | Major | Development | 2 | ||
| Story | Major | Ready | 2
|
Key | Summary | Issue Type | Priority | Status | Story Points (10) |
Story | Minor | Ready | - | ||
Story | Minor | Ready | 2 | ||
Story | Minor | Test | 5 | ||
Story | Minor | Ready | 3 | ||
Story | Minor | Ready | - |
*Summary details removed intentionally
Hey,
even if the question is quite old, but as I was wondering about the JIRA numbers myself, maybe my answer helps others too:
Greetings
We'd like to have an official answer for this as well! In the meantime...
Our current working assumption is exactly what BK wrote - ignore the points for stories add after the sprint started. However, we have an additional caveat for story points that have changed during the sprint. These are represented in the report as two numbers with an arrow between (e.g., "42 -> 45").
So, when calculating Commitment exclude issues added after the Sprint starts (those with a '*") AND use the number on the "left" if the story points were changed during the sprint.
One thing I am not sure of is what happens if a Story was added to the Sprint after it began and then removed before the Sprint ended. I haven't looked into it but I assume that it just doesn't appear.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Janis,
Sorry for the delay in response. Please find the details below:
Committed story points in EazyBI:
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.