Want a simple report showing time spent on which activity in a given period

Ole Henrik Rostad August 10, 2020

I need a report mostly for a retrospective view what we spent our time on last period (14 days). Main interest is time spent on new dev, improvement, bug fix, task, support etc. 
So I'm thinking a simple hour report from Tempo filtered by project, grouped by project and issue as it would be natural to use issue type to measure activty and time spent. That report does not show issue type in Jira view but it's part of excel export. But that again creates some work as I must group the data toghether, remove unwanted rows etc etc. thi smust be a commen required, any easier way to do this? We have Tempo and BigPicture plugins.   

2 answers

0 votes
Alexander Eck [Tempo]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 18, 2020

Hi Ole,

we have a feature request for this and I would encourage you to vote on it: https://tempo-io.aha.io/ideas/T-I-295 (need to have an account in our portal to vote for it).

BR

0 votes
Marcin Geb _SoftwarePlant_
Atlassian Partner
August 10, 2020

Hello

I'm a BigPicture team member, so here's how I'd run the tracking of Time spent in BP:

  1. I would divide the timeline into Sprints, iterations, or whatever time boxes you wish. 3 ways of setting up sprints in BigPicture/BigGantt.
  2. Then I added the 'Time spent' column to the view (View > Column views > Manage column views), see fig. 1, and applied SUM [no parent] aggregation here.
  3. As you can see, Development-related tasks took 115 hours during 20 Jul and 2 Aug, while Bug fixing cost only three hours, as green arrows indicate.

Obviously, this is a way to go for those who wish to combine planning ahead with the retrospective approach you mentioned.

What do you think?

Fig. 1

spent-time-tracking.png

 

Time tracking in BigPicture and BigGantt

Progress tracking with BP/BG