Hello,
I am trying to create a dashboard for the previous sprint. I need to show how many issues were in the previous sprint and their status when sprint was completed. I can get the count and issues for completed sprint but how would I get the statues at the time of sprint completed. When I create the chart issues show current status. Can you please help.
For example - Issue X was assigned to Sprint 1 and it was in to-do status when sprint was completed
Today the X is now added into the in-review status
I want to show the status of Issue X at the time of sprint completed i.e. To-do.
Hope it makes sense.
Thanks
Hey @Shail Choksi
It looks like the Sprint Report is the reporting you're looking for.
Please, refer to Sprint Report documentation.
Cheers.