What Report should I use to see what Issues were in a Sprint at the time the Sprint was started?

Cheryl Young January 2, 2019

I'm doing an analysis of a recent Sprint and would like to see what Issues were present in the Sprint at the time it started.  I've had a look at the Burndown Chart and the Sprint Report but it seems that Issues are missing from these reports?

2 answers

1 accepted

0 votes
Answer accepted
Alexey Matveev
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 2, 2019

Hello,

If you have a next-gen project, you can see it in the Burndown report.

if you have a classic project, then you should see it in the Burndown chart. If an issue was added to a sprint, it will be written: issue added to sprint. 

Cheryl Young January 2, 2019

Thanks for that.  I have a classic project so have looked at the Burndown Chart but there are a large number of Issues missing from this chart, any ideas why this would be the case?

Alexey Matveev
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 2, 2019

I am not sure, what you mean by missing issues. Here is how my Burndown chart looks like:

Screenshot 2019-01-02 at 14.46.57.png

Cheryl Young January 2, 2019

The report I see only lists 19 Issues added to the Sprint from the time it started, however I know there were closer to 50 Issues added.  I can't figure out why they aren't all listed.

Alexey Matveev
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 2, 2019

Could you have a look at the Sprint value for an issue, which is absent? What it the sprint value there?

Cheryl Young January 2, 2019

I've checked the Sprint value of an absent Issue and it has the correct value and so should appear in the Burndown Chart but it's not, not sure why that's the case?  If I use the Issue Navigator and filter to show all Issues in the Sprint a list of 74 Issues appears, however when I use the Burndown report only 25 Issues are accounted for.

Cheryl Young January 2, 2019

I've noticed that the missing Issues all have a status of 'Closed'.  Does 'Closed' Issues not appear in Reports?  If this is the case, do you know if there is anyway to include the Closed Issues?

Alexey Matveev
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 2, 2019

Could you go to board settings -> general tab and check the filter. Does the filter select Closed issues?

Cheryl Young January 2, 2019

Got it!!  Thanks for all your help Alexey! 

Alexey Matveev
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 2, 2019

You are most welcome! If my answer helped you, kindly accept my answer.

0 votes
Nishanth Thimmareddy _Appfire_
Atlassian Partner
January 2, 2019

Hi @Cheryl Young,

You can look at the Sprint Report which also reflects issues that are added or removed from the sprint. You can view all the issues added/ removed after the sprint started in the Issue Navigator too.

Hope that helps!

Regards,

Nishanth T