What is the concept of blocks or blocked by between two issues in jira?

Hammad Saeed Lodhi
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
March 5, 2019
I need to understand the concept of blocks and blocked by link between two issues in jira

1 answer

9 votes
Sebastian Brudziński
Atlassian Partner
March 5, 2019

Simply put, this is a relation between the two issues, in which one depends in some way on the other.  Eg. you have tickets:

  • XYZ-1 Research ABC 
  • XYZ-2 Implement ABC

You could say that XYZ-2 is blocked by XYZ-1, because you don't want to start implementation of feature ABC until research is done.

Best,
Sebastian.

Business Solutions & Services March 7, 2019

Thanks Sebastian for the clear answer of this.

This is very much clear now.

Like # people like this
Joe Bowen May 20, 2021

Does an open bug block the progression of a Task?