A custom field was created in the system: [CHART] Time in Status
Which is returning the following information to a ticket, for example:
10090: 1 transition, total time taken: 5,574,070 units.
10051: 1 transition, total time taken: 3,142,880 units.
10050: 1 transition, total time taken: 2,230 units.
10096: 2 transitions, total time taken: 430,647,938 units.
10044: 1 transition, total time taken: 0 units.
10136: 1 transition, total time taken: 4,216,022 units.
How to find out which unit of measurement this 'unit' is?
And what is the way to associate the IDs with the status as a From>To?
Hi @Luã Prata
Can you clarify which add-on are you using?
I'm representing Time in Status add-on for Jira
In our add-on the Format option lets you select the time format of status duration:
DHM (Days, Hours, Minutes)
HM (Hours, Minutes)
h:m (hours:minutes)
M (Minutes)
Decimal Hours
Decimal Days
Decimal Weeks
Business DHM,
Business Decimal Days,
Business Decimal Weeks.
So you won't be confused.
Try add-on has a 30-day free trial version and free up to 10 users.
Please, let me know if you have any questions
Hope it helps 😌
Hi @Luã Prata -- Welcome to the Atlassian Community!
That is not a built-in Jira field, and was likely added by a marketplace addon / app.
Perhaps work with your Jira site admin to identify the addons and then contact the vendor to check their documentation.
Kind regards,
Bill