What things/ checklist we need to think before Decommisioning an on Prem Server

Ruchi Uppal October 25, 2023

What are the things or a checklist we should have before decommissioning the on Prem server/instance since now our Jira is in the data center now after the migration took place? 

2 answers

0 votes
Ruchi Uppal October 26, 2023

Thanks, Craig for responding I figured out that before decommissioning the On-Prem Jira we need to make sure that

-URLs should have been migrated over

-and make sure that all the DNS entries have been transferred or any are remaining. 

 

We had an On-Prem Jira Instance migration to Jira Data Center and we wanted to make sure that before we Decommission the On-Prem Instance we checked a few things like URL, and DNS entries before it's turned off completely. 

0 votes
Craig Nodwell
Community Champion
October 25, 2023

Hi @Ruchi Uppal what migration?  Server to DC is a simple license swap.  Could you please describe your ask a bit more.