My problem is
1) I have created an epic in Jira
2)In the automation process, when an epic is created, it automatically creates a task, which works as expected
3)My goal is to create a sub-task under the same task that was automatically created
Let me know it is possible or not?
Hi Gaurav - Welcome to the Atlassian Community!
Sure, you can do that. Add a Branch after you create the task base on the recently created issue (being the Task).
Then add a new action for Create issue and populate with the information for the sub-task. Be sure to use the recently created issue as the Parent (or it might say Trigger issue).
@John Funk It's working fine, Thank you for your reply
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Gaurav Jayant , i dont have an answer for your question, but i would love if you could tell me how you automate the task creation when creating an epic please?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.