I've got a plan in JIRA Portfolio tied to many JIRA projects. Today I did an 'update from date..."
It seems that for many JIRA issues were updated with incorrect original and remaining estimates.
I did not think what I was doing would push any updates from JIRA Portfolio or change any estimates.
I DID NOT do a "planned update to project(s)..."
Under plan config, data, sync: Update estimates is set to off.
Under keep backlog items in sync, Summary, Description, and Estimates fields were checked. Did having estimates checked cause this?
In short, my goal is to only go in one direction - Bring updates from JIRA to JIRA Portfolio (not vice versa).
I only want to update the work logged, status change, and progress. I don't care about updating the estimate if it might cause issues like this.
Can anyone advise?
Same issue happening to us - Portfolio "Update from date" is editing the "Original Time estimate" (e.g. adding 32 mins or so) in JIRAs and setting the "Remaining Time Estimate" to the same value as the Original Time Estimate - which makes it look like the JIRA still has it is affecting the JIRA sprint burndowns - but we need to "Update from date" in portfolio in order to accurately predict plans from here forward.
Note: as recommended in https://confluence.atlassian.com/jiraportfoliocloud/regular-plan-updates-715263783.html - we are using the date of the last sprint:
"If you are working with iterations, it is recommended that you use the planned start date of the upcoming sprint as the update date."
Can you explain why the start date of the next planned sprint must be used?
Note: we did initially think the adjustment of time was related to different number of hours set in JIRA (8h) and Portfolio (7.5h) - but these are now set to 8h.
What I've noticed is that doing "update from date" in portfolio that includes a story which has a sub-task causes the sub-tasks remaining estimate to be accumulated again into the story's estimate.
Steps to reproduce:
Seems pretty well broke to me. I've read in the bug description that this is not likely to be fixed, but this behavior in portfolio is clearly dangerous. Anyone know how to vote for this bug or report the above reproduce steps as a new, special case bug?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Update from Date is killing me. Along with 500 other questions on exactly what the behavior is with the configuration options and best practices.. Hope you get an answer for this one.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I can confirm the same behavior. This behavior has not caused us to abandon sub-tasks as it has caused one User Story to update remaining hours over 1000, after repeated 'update from date'. This is frustrating.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.