When utilizing WBS Gantt Chart to upload a MS Project file into Jira Tasks are imported backwards

bstyck
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
March 8, 2022

When using WBS Gant Chart to upload a MS Project schedule into Jira all of the tasks are imported backwards for example with the 1st task last and the last task first. Why is this and are there setting within WBS Gant Chart or Jira to prevent this? 

1 answer

1 accepted

0 votes
Answer accepted
VPN担当者
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 8, 2022

Hello,

Can you check "View link in reverse" and see if the problem will be solved?

Jira configuration > Apps > WBS GANTT-CHART > Issue > Edit > Check "View link in reverse" > Update

スクリーンショット 2022-03-09 10.53.07.png

bstyck
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
March 10, 2022

Thank you very much.  That was the issue.  