This question is in reference to Atlassian Documentation: Committing your plan changes
I am a first time user of Jira-Portfolio and I am trying to review before committing my changes in my plan. I recall that when I initially trialed Portfolio, I was able to review my changes to my plan before committing them. For some reason, I am unable to do so now.
The bubble with the number of changes I have made is not orange (as in the article), but grey and instead of "uncommitted changes" next to the number, it simply has "recalculate". So, each time I try to click on the grey bubble with the number of changes, it recalculates my plan instead of opening the window with a list of my changes to review and commit.
My company is running JIRA v 7.1.9 and Portfolio v 2.0.5, which was recently updated.
Any ideas on what I need to do to bring the review of "uncommitted changes" back?
Hey Christine - this sounds like you're in a Portfolio classic plan, vs. a Portfolio live plan. Classic plans (pre Portfolio 2.0) had a recalculate up the top, with the new integration in live plans and the uncommited changes capabilities, we've removed that. If you create a new plan, make sure you go directly through the plan creation wizard, only the small link at the bottom takes you to creating a classic plan. Not sure how much work you put into this already, but the best approach would be to start a new (live) plan.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.