Why am I losing sprints and Epic data when importing my Agile data into a new JIRA Environment?

Paul DiNunzio
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 23, 2015
 

1 answer

0 votes
David Di Blasio
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
February 23, 2015

Hi Paul, 

Currently the only way to import Agile data is through an xml backup/restore. The project import function does not include activeobject data. Here's a feature request for the addition of this functionality. 

https://jira.atlassian.com/browse/JRA-28748

 