Its making me nuts right now
I have tasks that are in the backlog that I move up to a current sprint (starts tomorrow). The Sprint has 13 tasks...when I move these into it, it knocks it up to 18. When I move to the work or report window and then come back.....the sprint is back at 13 and the tasks i just moved are back in the backlog.
The fix versions are right (our current release) and the sprint version is in "fix version" as well as the current sprint. yet it will not stay.
WHY?
I guess yo have to provide some more information, like what is your board filter setup like? What kind of permissions do you have?
Usual suspects if you begin searching here is that the filter is not ordered by rank and/or people do not have project admin rights on *all* projects the filter touches.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.