Why are parent tasks in a sprint no longer separate?

VICTUS September 3, 2023

Previously, my tasks and subtasks in a sprint were clearly separated, but now it has turned into one big pile. How can I fix this?

 

2 answers

0 votes
Trudy Claspill
Community Champion
September 3, 2023

Hello @VICTUS 

Are you saying that your view of the specific board you shared has changed? Or are you comparing the view of this board to other boards?

It appears to me that the information is displaying as it normally should when you are choosing to show subtasks on your board, and have Swimlanes set to None.

When you choose to show subtasks on your board, each subtask will show as a card. Above the subtask will show a header with the ID and Summary of the parent task if the parent task is in a different status. The parent task will show as a card in the column that matches its status.

Screen Shot 2023-09-03 at 5.37.18 PM.png

If you had your Swimlanes set to Stories then the parent task would appear as just a header and its subtasks would appear in a horizontal group below it. Each task would be a new horizontal group.

Screen Shot 2023-09-03 at 5.34.52 PM.png

Can you describe how this is different than what you previously saw?

Have you changed the Swimlanes setting for your board?

VICTUS September 4, 2023

Thanks for your description! Indeed, I need to do it as described in the second option, but I don’t know how.

Trudy Claspill
Community Champion
September 4, 2023

If you are an Administrator for the board you can click the ... button in the upper right corner above the board and select Board Settings. In the next screen select Swimlanes. That will give you the option to specify what you want to use for Swimlanes.

0 votes
VICTUS September 3, 2023

image.png

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
STANDARD
PERMISSIONS LEVEL
Product Admin
TAGS
AUG Leaders

Atlassian Community Events