Why can't I set an task as unasigned?

Clara Anna Miranda
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 23, 2021

All tasks, stories and epics that are created in my project starts assigned to me and I see an error saying "All itens must be assigned" when I try to set it as unsigned.

It looks like there's some kind of rule ou automation who sets this rule, but I didn't find nothing relacted in the project automation rules.

This issue is very annoying because I can't have the view about the itens that nobody is working yet, someone have any tip about how can I fix this?


image.png

1 answer

1 accepted

2 votes
Answer accepted
abelalia87
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 23, 2021

Hi Clara, 

If you are an admin go the global settings [upper right side settings], then select System, then General Configuration, then Edit Settings. 

Allow Unassigned Issues.png

Hope that helps. 

Clara Anna Miranda
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 23, 2021

Thank you very much, this solved the problem!