Why does my Start Date value keep changing?

Gunyong January 6, 2023

Hello,

The Start Date value is automatically changed whenever I add a label to an Initiative, Epic or Task, which in turn pulls it in my Advanced Roadmap/Plan through a query. Below are the steps to reproduce:

1. Create Initiative, leave Start Date blank

2. Add label

Result: the system makes the Project Lead automatically change the Start Date. See below screenshot:

Start date issue pic 1.png

 

Another occurrence of this issue is on the Advanced Roadmap where I try and correct the Start Date but to no avail. After removing the Start Date, the Start Date is automatically rolled up. When saving the changes to Jira and doing a refresh the values are changed again. See below:

Start date issue pic 2.png

This happens to existing items in the plan and also right after creating new items. No matter if they're labelled or not. The thing they have in common, despite the project they're from, is that they're connected to this Plan and are created by me.

 

 

Note: a Start Date prior to 2023 remains unchanged. See below picture:

Start date issue pic 3.png

 

Any support to resolve this is greatly appreciated. 

Thanks in advance!

Cheers,

Victor

2 answers

0 votes
Ste Wright
Community Champion
January 6, 2023

Hi @Gunyong 

Can you check...

  • If an Automation Rule is setting the Start Date and the Estimate field? This could be Project-level or Global
  • If a Workflow Post Function is doing this?

Have you also checked with the Project Lead, see if they know why this might happen?

Ste

Gunyong January 6, 2023

Hi @Ste Wright

Thanks for the quick reply!

There are no Automation Rules set that affect labels or start date.

As for the Workflow, there are no special rules setup. It's just the plain To Do > In Progress > Done.

There are 3 projects included in my Plan and the issue does not discriminate between them. I am the Project Lead of 1 and the other Project Lead also doesn't know what might be causing this.

Thanks for having a look into this!

Ste Wright
Community Champion
January 6, 2023

Hi @Gunyong 

Do you have Scriptrunner or a similar scripting App, given it's Server?

Could a script be causing this to happen?

Ste

Gunyong January 6, 2023

Hi @Ste Wright

I don’t know what scripts might be running so I’ll check with my IT team when they’re back on Monday and let you know. 
Thanks for the replies and have a good weekend!

Cheers

Like Ste Wright likes this
0 votes
Vamsi Kandala
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 6, 2023

Hi @Gunyong

Welcome to the community!

Did you check whether any automation rules are present that is triggering when the label value is changed and updating the State Date accordingly?

Thanks,
Vamsi

Gunyong January 6, 2023

Hi @Vamsi Kandala,

Thanks for the warm welcome and quick reply!

I just checked and there are no automation rules that relate to the issue I'm facing. 

Cheers

Like Vamsi Kandala likes this

Suggest an answer

Log in or Sign up to answer