Right now there is a sprint in progress and I needed to extract a report from the this sprint with stories and tasks. Whenever I try to extract a report it doesn't show any stories or tasks from this sprint. What am I doing wrong ?
Hi @Sara Shahin ,
Welcome to the Atlassian Community.
Exactly which report are you trying to generate?
Do you have open and resolved stories/tasks in the sprint?
Best regards,
Kris
Hello,
Welcome to the community :)
The Sprint Report points to information included initially in the sprint (what the team actually committed to). That being said, if you add an issue with zero story points to a sprint, start the sprint and then change the story points, you will see the initial value in the sprint report.
Statuses are not properly mapped to Columns on the board's configuration
Thank You,
Prachi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Can we assuming you're talking about this report ?
Project > [Board] > Reports > Sprint Reports
The sprint reports offer data such as
Hence, the sprint has to be completed to produce these reports.
What you could do, to
project = [projectKey] and Sprint = [SprintID]
Use the sprint insights for a health check of your current sprint.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.