Hi, is there a way to limit the number of child issues in an epic or the number of issues form a specific type in a scrum backlog?
Thanks!
@Yoni Farin - hi Yoni! If you're managing your work in a kanban board, you can limit work in progress (WIP) in that board's settings page.
If that's not what you're looking to do, can you rephrase your question? Appreciate any insight!
Hi @Dave Liao
Thanks for the quick reply. We are not using kanban, we are using large scale scrum with one backlog for all issues (bugs and stories). Thoes issues are child issues of epics. I'm looking for a way to limit the number of child issues in an epic or limit the global amount of issues from a specific type e.g., bug in the backlog.